|
|
Terminals
22.6.09
Brigadier Lloyd (originator of conversion) said
Transwatch states that
In its submission to the Select Committee, Transwatch referred to the
nimble bus versus the cumbersome train. A complete rebuttal of their submission
may be found on www.transportmyths.co.uk
(then click Select-8)
In its web site, Transwatch
claimed that ‘probably a bus
would use a terminal space 3-4 times as efficiently as the train. With similar
calculations, it can be shown that, in terms of both capacity & use, road
transport out-performs rail by a factor of 3-5 across the network. This is
important. It suggests that alternatives to rail are not only technically
feasible, they would be technically highly efficient’. (Journal of the
Institute of Economic Affairs Volume 24, No. 2, June 2004). Again that
mysterious plan - with no costs, nor building timescale.
Transwatch claimed on Radio2
(Jeremy Vine programme, 24 July 2007) that ‘its calculations showed that
only 25% of the space of a rail passenger terminal would be required for buses
replacing trains’. No formula or costs, or timescale was given to support
this wild claim, which were not challenged. It did not mention that it
envisaged them having three levels, or for buses to ‘do a loop beyond the
terminal’.
According to Transwatch: ‘terminal
capacity is a separate issue and more difficult to demonstrate simply’.
It is crucial and only difficult in the absence of a timetable based on a full
analysis of the precise journeys which passengers make. Conversion proposals
have tended to ignore the practicalities of operation, which any transport
operator - road or rail - would regard as the first essential step. Lloyd
sought to dispense with timetables for the very reason that they would prove
the impracticability of his dream
Fact 1 – Only one study
has been published of a rail route conversion – part of the route from
Fact 2 – This study
included a plan drawing of the station (
Fact 3- The route from
Fact 4 - The idea of multi
floors has not been thought through. The time required by buses to pass to/from
upper floors has not been evaluated. There are no drawings, no costs, no
assessment of the area that would be occupied with ramps. It is overlooked that
local authorities can block such schemes as they did BR plans to build above
Fenchurch Street & Euston, and would be very likely to do so, especially
with stations that are listed buildings with large roof spans. It would be
costly. Every terminal (over 50) will be out of action for at least a year.
Some large through stations will require multi-story replacements to avoid
buses clogging the ground floor area. Passengers will be diverted to existing
roads, which will double up as “terminals”. As there will be
hundreds to be rebuilt simultaneously, along with increasing clearances of many
tunnels & bridges, removing rail infrastructure and laying concrete, the
entire system would be out of use for years.
Fact 5 - To ‘do a loop,
beyond the terminal’ – as the conversion mini lobby advocates - is
ridiculous. The narrow congested streets around most major city stations make
this totally impractical. They would have to cross pedestrian flows outside the
terminal, leading to more accidents. Some terminals are not at street level
anyway, and surrounding streets would give no space for ramps. Buses would
return to the terminal at unpredictable times.
Fact 6 – ‘Managing
roads to avoid congestion’ has yet to be achieved. It should be proven on
an existing road that has widths similar to a railway double track, before
attempting it from a converted city rail terminal.
Fact
Fact 8 - Claims must not start
with ‘probably’ and end with certainty as they do with many
conversionist claims.
Fact 9 – No mention is
made of the manpower required to clean buses, lorries, bus stations, etc., nor
to maintain and clean toilets, waiting areas, etc. Existing railway manpower is
included in total railway staffing with which the crudest
“comparisons” were – occasionally - made with a handful of
lorry or bus drivers. The analogous manpower required to maintain and repair
structures (and route) are completely ignored.
See also “Railway Conversion
– the impractical dream”
bravenet.com